ALOGY tools
Back to tools

Residential cable sizing

Residential electrics

Register the whole house — supply, panels, rooms and circuits — and see on the distribution tree what meets the criteria, what needs adjustment and what is still to be checked, per NBR 5410.

Made for installations in Brazil: ABNT NBR 5410 (aligned with IEC 60364-5-52) and Brazilian load-estimation rules. Outside Brazil, use it only as a reference and follow your country’s code.

Saved only in this browser, not in your account
Needs adjustment3 circuits need adjustment · 0 with checks pending · 3 meet the checked criteria
Design and installation by a qualified professionalLimits
  • Support for study and preliminary sizing: the final design and the installation are by a qualified professional, following the standard and the utility’s rules.
  • It does not check selectivity, earthing, special site conditions or the utility’s rules.
  • Technical support: check the data you entered. The design, the configuration and the decision to apply the result belong to the responsible professional, with the standard and the manufacturer’s data.

House totals

Installed load
10.7 kW · 10.8 kVA
Demand considered
10.8 kVA
Phase A
54.1 A
Phase B
39 A
Neutral (estimated)
20.7 A
Imbalance
28 %
Service entrance breaker
63 A

Demand criterion: installed load, no factor (on the safe side). Phase-neutral circuits add to their own phase; phase-to-phase circuits, to both.

Distribution tree

100%
  • Met
  • Needs adjustment
  • Pending
  • Busbar: everything leaving it is in parallel
  • SPD: in parallel, to earth
  • Cable metres, one way; at the points, to the panel
  • Planned new circuit

Tap a breaker or a point to see the details and edit. The − and + buttons fold and unfold the RCD groups.

What needs adjustment or checking

PendingService entrance
  • Pending

    Enter the utility: the service entrance category (breaker and cables) follows its supply standard.

    Utility

  • Pending

    Short-circuit current at the delivery point not entered: the short-circuit and breaking-capacity checks are pending.

    Utility

    Ask the utility for the prospective short-circuit current at the delivery point; many state it in their supply standard.

Needs adjustmentDistribution panel
  • Needs adjustment

    Overhead service line: the standard requires an SPD in the main distribution panel (or at the entrance) where there are more than 25 thunderstorm days a year (AQ2), the case of most of Brazil. Connected from the phases and the neutral to the earth bar.

    Requirement of the standardNBR 5410, 5.4.2.1 e 6.3.5.2

Needs adjustmentC1 · Living room outlets
  • Needs adjustment

    The 20 A breaker does not properly protect the 2.5 mm² cable in “C1” (capacity 16.8 A in these conditions).

    Requirement of the standardNBR 5410, 5.3.4

  • Needs adjustment

    Grouping of circuits (3 circuits together, factor 0.7) lowered the capacity of this cable from 24 A to 16.8 A.

    Requirement of the standardNBR 5410, tabelas 40 e 42

Needs adjustmentC4 · Bedroom outlets
  • Needs adjustment

    The 20 A breaker does not properly protect the 2.5 mm² run “Branch to bedroom 1” (capacity 16.8 A): the reduced section needs its own protection or a smaller breaker.

    Requirement of the standardNBR 5410, 5.3.4

  • Needs adjustment

    The 20 A breaker does not properly protect the 2.5 mm² run “Branch to bedroom 2” (capacity 16.8 A): the reduced section needs its own protection or a smaller breaker.

    Requirement of the standardNBR 5410, 5.3.4

  • Needs adjustment

    Grouping of circuits (3 circuits together, factor 0.7) lowered the capacity of this cable from 32 A to 22.4 A.

    Requirement of the standardNBR 5410, tabelas 40 e 42

  • Pending

    Phase of circuit C4 not entered: the house calculation assumed B.

    Calculation assumption

    Follow the wire from the breaker to the busbar or use a voltage tester: find which phase (A, B or C) the circuit is connected to.

  • Pending

    Protective conductor (PE) of circuit C4 not entered.

    Requirement of the standard

    Check that the protective conductor (green-yellow or green) reaches the outlets and equipment of the circuit.

Needs adjustmentC6 · Bathroom electric shower
  • Needs adjustment

    “C6”: the current in this run (26.3 A) exceeds the capacity of the 4 mm² cable in these conditions (22.4 A).

    Requirement of the standardNBR 5410, tabela 36 e 5.3.4

  • Needs adjustment

    The 32 A breaker does not properly protect the 4 mm² cable in “C6” (capacity 22.4 A in these conditions).

    Requirement of the standardNBR 5410, 5.3.4

  • Needs adjustment

    Grouping of circuits (3 circuits together, factor 0.7) lowered the capacity of this cable from 32 A to 22.4 A.

    Requirement of the standardNBR 5410, tabelas 40 e 42

Data to confirm on site

  • Kitchen: above the sink worktop, at least two outlets (at the same point or not).
  • Television: power estimated by the library; confirm it on the nameplate or in the manual.
  • Computer: power estimated by the library; confirm it on the nameplate or in the manual.
  • Short circuit of circuit C1 not checked: the short-circuit current at the delivery point (utility) is missing.
  • Circuit C2: estimated length; measure on site to confirm the voltage drop.
  • Short circuit of circuit C2 not checked: the short-circuit current at the delivery point (utility) is missing.
  • Air conditioner 12,000 BTU/h (inverter): power estimated by the library; confirm it on the nameplate or in the manual.
  • Circuit C3: estimated length; measure on site to confirm the voltage drop.
  • Short circuit of circuit C3 not checked: the short-circuit current at the delivery point (utility) is missing.
  • Circuit C4: estimated length; measure on site to confirm the voltage drop.
  • Short circuit of circuit C4 not checked: the short-circuit current at the delivery point (utility) is missing.
  • Micro-ondas: power estimated by the library; confirm it on the nameplate or in the manual.
  • Air fryer: power estimated by the library; confirm it on the nameplate or in the manual.
  • Refrigerator: power estimated by the library; confirm it on the nameplate or in the manual.
  • Circuit C5: estimated length; measure on site to confirm the voltage drop.
  • Short circuit of circuit C5 not checked: the short-circuit current at the delivery point (utility) is missing.
  • Electric shower 5500 W: power estimated by the library; confirm it on the nameplate or in the manual.
  • Electric shower 5500 W: wired straight to the point, without a plug (NBR 5410, 9.5.2.3).
  • Short circuit of circuit C6 not checked: the short-circuit current at the delivery point (utility) is missing.
  • Distribution panel: with 6 circuits, leave spare space for at least 2 future circuits, and allow for that reserve in the feeder (NBR 5410, table 59).
  • Distribution panel: estimated feeder length; confirm on site.
  • Neutrals: each circuit on an RCD takes its neutral from that RCD, never sharing a neutral with circuits outside it; the protective conductor (PE) never passes through the RCD.

Grouping the circuits under RCDs

Comparison of arrangements (technical recommendation). The standard requires a 30 mA RCD on circuits in wet and outdoor areas and on kitchen and laundry outlets (5.1.3.2.2); how to group them is a design choice. On a shared RCD, a leak in any circuit switches all of them off, and the small normal leakages of the appliances add up.

Distribution panel
ArrangementRCD devicesSwitched off by one trip (most)Most loaded RCDRequired ones without RCD
As registeredRCD: C5, C612 circuits42 A (RCD of at least 63 A)✓ none
One RCD for all circuitsRCD: C1, C2, C3, C4, C5, C616 circuits55.4 A (RCD of at least 63 A)✓ none
One RCD for the circuits that require it and another for the restRCD: C5, C6 · RCD: C1, C2, C3, C424 circuits42 A (RCD of at least 63 A)✓ none
An RCBO on each circuit that requires an RCD and one RCD for the restRCD: C1, C2, C3, C4 · DDR: C5, C634 circuits14 A (RCD of at least 25 A)✓ none

The RCD current also cannot be lower than that of the breaker protecting it; check the manufacturer's coordination table.

Bill of materials

Only for new circuits and existing circuits whose cable is replaced. Route is the cable path (one way); each conductor's length adds the slack and the connections in the boxes.

By circuit
CircuitReasonRouteConductors
C3 · Living room air conditionerNew circuit16 mPhase 2.5 mm²: 35.8 m · PE protection (green-yellow) 2.5 mm²: 17.9 m
C5 · Kitchen outletsNew circuit12 mPhase 2.5 mm²: 14.7 m · Neutral (light blue) 2.5 mm²: 14.7 m · PE protection (green-yellow) 2.5 mm²: 14.7 m
C6 · Bathroom electric showerCable replacement10 mPhase 10 mm²: 22.6 m · PE protection (green-yellow) 10 mm²: 11.3 m
Total conductors to buy
ConductorCross-sectionLength
Phase2.5 mm²50.5 m
Phase10 mm²22.6 m
Neutral (light blue)2.5 mm²14.7 m
PE protection (green-yellow)2.5 mm²32.6 m
PE protection (green-yellow)10 mm²11.3 m

Criteria and sources

  • Requirement of the standard
  • Manufacturer
  • Utility
  • Technical recommendation
  • Calculation assumption

Made for installations in Brazil: ABNT NBR 5410 (aligned with IEC 60364-5-52) and Brazilian load-estimation rules. Outside Brazil, use it only as a reference and follow your country’s code.

Reference: ABNT NBR 5410:2004 (corrected version 2008). Checked against the text of the standard: current-carrying capacity (table 36), temperature factors (table 40) and grouping factors (table 42), loaded conductors (table 46), minimum cross-sections (table 47), protective conductor (table 58), spare space (table 59), coordination Ib ≤ In ≤ Iz (5.3.4), voltage drop (6.2.7), RCD (5.1.3.2.2), SPD (5.4.2.1, 6.3.5.2 and tables 31 and 49) and forecast of loads, points and division of circuits (9.5.2 and 9.5.3). Conductor resistances: Prysmian's low-voltage cable sizing guide (rev. 9).

Requirement of the standard: an item NBR 5410 asks for. Manufacturer: data from the device catalogue (curve, Icn, I²t, RCD × breaker coordination). Utility: a rule of the supply standard (service entrance category, incoming breaker, demand factors, prospective short circuit). Technical recommendation: good practice the standard does not mandate. Calculation assumption: value adopted when the data was not entered.

Flexible copper conductors (class 5) with PVC insulation (70 °C), using the maximum resistance of NBR NM 280, the highest of the usual classes, so the voltage drop errs on the safe side; the reactance, small in residential circuits, is not added. Phase-neutral loads add to their own phase; phase-to-phase loads, to both. The feeder drop adds the phase and neutral drops (on the safe side).

Short circuit: checked only with the prospective current given by the utility; the let-through energy (I²t) depends on the breaker catalogue. Selectivity between devices and earthing (rod resistance, equipotential bonding) are not calculated here.

The values suggested by the appliance library are estimates: confirm power and voltage on the nameplate or in the manual. BTU/h is the cooling capacity of the air conditioner, not its electrical power.

Reference calculation from the data entered; it does not replace a design by a qualified professional, the standard, the manufacturer's catalogue or the utility's rules.

Residential cable sizing: cable, breaker and RCD based on Brazilian NBR 5410

Register the whole house — service entrance, panels, RCDs, SPD, rooms and circuits — and see the distribution tree with what meets the criteria, what needs adjustment and what is still to be checked. For a single circuit (shower, outlets, air conditioner), the quick calculation gives cable, breaker, RCD and the diagram with the conductor colours.

Where it helps at work

  • Check the circuits of an existing house without losing the record of what is installed, and compare them with a checked proposal.
  • See the effect of a new shower or air conditioner on the panel, the feeder and the service entrance breaker.
  • Plan the circuits of a refurbishment, with smaller-section branches, RCD groups and sub-panels.
  • Show the client, with the tree and the report, why the cable or the RCD has to change.

Worked example: 5500 W shower at 220 V

A 5500 W electric shower at 220 V (two phases) is in the bathroom, 12 m from the panel. The conductors run alone in a conduit embedded in the wall, at 30 °C. Which cable, breaker and RCD?

Data
CircuitElectric shower
RoomBathroom
Supply220 V · phase and phase
Power5500 W
Length (one way)12 m
InstallationEmbedded in conduit (B1)
Result
Design current26.3 A
Cable4 mm²
Breaker32 A · curve B · two-pole
Residual-current device30 mA · 40 A · required
Corrected cable capacity32 A
Voltage drop3.73 V (1.7 %)

How to read it

The shower draws 25 A at 220 V; with the voltage at the top of the normal range (231 V, 5 % above), it reaches 26.3 A, the design current. A 2.5 mm² cable would carry only 24 A, less than the 32 A breaker: the current-carrying capacity leads to the 4 mm² cable. The 1.7 % drop is well below the 4 % of a final circuit, and the 30 mA RCD is required because it is a bathroom.

Limits and cautions

  • Copper conductors with PVC insulation, as in houses and flats. For motors and industrial installations, use the industrial cable sizing.
  • Short circuit only with the prospective current given by the utility; let-through energy (I²t), selectivity and earthing depend on the manufacturer and the design. The service entrance category follows the utility’s standard.
  • It is a design aid: “meets the checked criteria” is not a compliance certificate and does not replace the electrical design signed by a responsible engineer.

Technical basis

Brazilian NBR 5410 (aligned with IEC 60364): current-carrying capacity with temperature and grouping corrections, minimum sections, coordination with the breaker (NBR NM 60898), voltage drop, 30 mA RCD and conductor colours.

  • ABNT NBR 5410 — low-voltage electrical installations
  • ABNT NBR NM 60898 — circuit-breakers for household installations
  • IEC 60364-5-52 — selection and erection of wiring systems
How we verify the calculations

Frequently asked questions

Can I use a larger breaker so it does not trip?

No. The breaker protects the cable: it must be at most the current the cable can carry. If it trips, the circuit needs a larger cable or another split of the loads.

Does the RCD replace the breaker?

No. The RCD protects people against electric shock; the breaker protects the cable against overload and short circuit. Where the standard requires it, both are used together.

Why did my shower cable come out larger than usual?

Because the tool takes the shower current with the voltage at the top of the normal range (5 % above nominal), when it draws more, and checks the current the cable carries embedded in the wall, with grouping and temperature, and the voltage drop over the real length. Check the shower manual as well and use the larger.